Construction of the Vista Bridge in 1926 was a tricky affair, as streetcar service along the Council Crest line was required to remain in operation without any disruption. The constrained right-of-way over the Jefferson Street ravine meant that it was not possible to build the new bridge adjacent to the old Ford Street bridge. Fortunately, the Portland City Archives contain many photographs that show how the construction was accomplished within these constraints, corroborating contemporaneous newspaper reports.

Map: Portland City Archives.

Map: Portland City Archives.

Above is a March 1922 map showing the right-of-way for the old Ford Street viaduct. It can be noted that the right of way varies from 48 to 50 feet wide, and the landings at the north and south ends are in almost exactly the same location as the current Vista Bridge. Any new bridge would have had to fit within this narrow right of way. The Ford Street bridge itself was 45 feet wide (with a 33-foot roadway and 6-feet plank sidewalks on each side), leaving very little room to maneuver.

The only real solution was to build the new bridge around the old one, leaving one streetcar track active on the old bridge until one half of the concrete deck on the new bridge was poured, cured and ready to bear weight. Then the streetcar track could be moved to that part of the new deck, while the second half of the deck was laid and the old bridge carefully taken down from underneath the new one.

Photo: Portland City Archives.

Photo: Portland City Archives.

Construction of the new bridge began in January 1926, and by April 13, 1926 had progressed to the point seen in the photo above, taken looking east from near the lower entrance to Washington Park. The formwork for the new bridge’s concrete arches can clearly be seen, but everything above that is still the old Ford Street structure. A Council Crest car can be seen crossing the old bridge. For a while, this photo had me convinced that the new bridge was built slightly to the west of the old one, but photos below show that is not the case.

Photo: Portland City Archives.

Photo: Portland City Archives.

The photo above, dated May 25, 1926, seems to show a steel beam from the old bridge in the foreground, still supporting the wood planks beneath the streetcar tracks, while forms for the new concrete deck are being assembled just a little further back, showing just how intertwined the two bridges were during construction.

Photo: Portland City Archives.

Photo: Portland City Archives.

This photo from August 10, 1926 seems to show Council Crest car No. 506 crossing the new bridge from south to north. However, newspaper articles make it very clear that streetcars continued to use the old bridge until September 2, 1926, after which they were transferred to a temporary track on the deck to the right of this photo (see next photo). You can see that the concrete deck on the left side of the bridge has not yet been poured: the track here is still supported by the steel supports of the old bridge, though its wooden decking has been cut so it is only just wider than the track. The old bridge is literally still there just beneath the new one.

Photo: Portland City Archives.

Photo: Portland City Archives.

This photo from September 3, 1926, one day after the temporary track was laid on the new concrete deck. It can be seen that the original track to the left is in the process of being taken up already. A Council Crest car waits to cross the bridge from south to north in the distance.

Photo: Portland City Archives.

Photo: Portland City Archives.

A view looking the other direction (north) on October 13, 1926 shows that the deck has been laid across the full width of the new bridge. The temporary nature of the active streetcar track across the bridge to the left of the photos is very evident here. By this time, work on dismantling the old steel bridge from beneath the new one had begun. The salvaged steel belonged to the contractors, Parker & Banfield, but the City of Portland soon purchased it from them to construct the Seventh Street/Terwilliger Viaduct in Burlingame.

Photo: Portland City Archives.

Photo: Portland City Archives.

Above is the view looking south on the same day, showing the new permanent double streetcar tracks embedded in the concrete deck of the new bridge.

Photo: Portland City Archives.

Photo: Portland City Archives.

Finally, here’s the completed bridge on January 8, 1927, about a month after its official opening (though some vehicles had driven over it prior to that date, and streetcar service had remained uninterrupted throughout the entire project). While the old bridge had been constructed and owned by the streetcar company, the new one was owned and maintained by the City of Portland, and a new streetcar franchise for the use of the bridge was drawn up to reflect this fact.